Gas Generator Reaches 100 Hour Milestone
March 29, 2005
On 29 Mar 2005, the CES gas generator
powering the Kimberlina Zero-Emission Power Plant reached
100 operating hours while providing electrical power to the
grid. 100 operating hours marks a significant step in demonstrating
the reliability and durability of the gas generator. The gas
generator and plant subsystems are currently completing tests
necessary to commission the power plant and begin long-term
durability testing.
|