    Gas Generator Passes 400 Operating Hours
   

July 30, 2005

On 28 July 2005, the CES gas generator surpassed 400 operating hours and 13 weeks of exporting electrical power to the grid. The CES combustor powers the Kimberlina Zero-Emission Power Plant near Bakersfield, CA, the world’s cleanest fossil-fuel power plant. The Kimberlina plant was commissioned in May 2005, and on 30 June 2005, the California Energy Commission gave approval to enter long-term durability testing of the CES gas generator. These milestones demonstrate continued CES progress in proving the reliability and durability of its gas generator.

     