|
In
August 2003, CES acquired an idle 5.5 MW biomass plant from
The AES Corporation. The power plant is located in Kern County,
CA, approximately 18 miles north of Bakersfield at the Kimberlina
Road exit. Due to air quality restrictions, the facility (Fig
1) had been out-of-service since 1986 but was in very good
mechanical condition.
Figure
1CES Kimberlina Power Plant
CES planned to initially use the plant as a demonstration
facility for CES gas generator and control system. Subsequent
gas generator work is expected to utilize alternative synthetic
gas fuels, including those derived from coal- and biomass
gasification.
In addition to internal company resources, CES obtained funding
and project support for the Kimberlina Power Plant demonstration
from the California Energy Commission, U.S. Department of
Energy, Air Liquide America, and Mirant Corporation.
|
|
The CES gas generator, developed in part under the US Department
of Energys Vision 21 Program, was installed at Kimberlina
in June 2004 (Fig 2). Upgrades and improvements to plant subsystems
(including piping, controls, electrical) were finished in
October. Significant new components included a natural gas
compressor, oxygen system, feed water pump, and a new condenser
for the steam turbine. All major systems have now been commissioned
except the new condenser (scheduled for early 2005).
A
high-pressure natural gas compressor was commissioned in early
September (Fig 3). It consisted of a new metering system,
gas compressor skid, and pressure regulating / relief valves.
Figure
3Natural Gas Compressor Skid
Oxygen system installation began in August, and following
extended testing, was commissioned in November 2004. Fig 4
shows blow-down of the cryogenic storage tank with nitrogen
to ensure its cleanliness during commissioning.
Figure
4Oxygen Tank blow-down
The 11,000 gallon oxygen system receives liquid oxygen by
truck, pumps the liquid to high pressure, vaporizes it, and
supplies gaseous oxygen under high-pressure to the Gas Generator.
Eventually, the oxygen system will be supplemented by an Air
Separation Unit to make oxygen on site. The oxygen system
(Fig 5) is surrounded by security fencing, cameras, and an
advanced (UV/IR) fire detection system.
Figure
5Oxygen Storage, Pumping, and Vaporization System
Similarly, a new, high-pressure feed water pump and de-mineralized
water tank, with associated piping and controls, was installed
in July. The unit was subsequently commissioned in August
(Fig 6).
Figure
6High-Pressure Feed Water Pump
Cold-flow tests of the gas generators oxygen, natural
gas, and cooling water circuits were performed in September
and October. These tests validated the gas generators
control system performance and calibrated gas generator valve
timing (Fig 7). Igniter circuit tests followed in early November
and first ignition was achieved on November 11th. Ignition
testing concluded November 23rd following five - in - a -
row demonstration.
Figure
75 MW Gas Generator
CES began a work-up to full power, hot-fire tests
of the gas generator on Dec 6th. A significant milestone,
first steam at low-load (20% power) was reached
three days later on Dec 9th. Gas generator testing in a stand-alone
mode (gas generator not connected to the steam turbo-generator
and all steam exhausted through a by-pass stack) will be conducted
until the full range of gas generator operations have been
demonstrated. Thereafter, the gas generator will be interconnected
to the Elliott steam turbine (Fig 8) and CES will be ready
to generate electrical power.
Figure
8Elliott 5.5MW Steam Turbine, Reduction Gear, and Electrical
Generator
A new condenser (Fig 9) and a liquid ring vacuum pump to
remove carbon dioxide will be installed early in January 2005.
This new condenser will enable sustained output of electrical
power to the grid. During the first phase of plant demonstration,
CO2 will be vented to atmosphere.
Figure
9Alstom Condenser prior to installation
The Kimberlina Power Plant team is led by Terry Chiles, a
former facility manager for General Electric with more than
twenty years experience. Terrys experience includes
17 years in the US Merchant Marine as Chief Engineer aboard
various steam and diesel ships and land-based power plant
experience at coal, natural gas, and biomass facilities in
the United States, Brazil, and India. Test Manager Andrew
Volondin is a former General Electric engineer with a Masters
degree in power plant engineering. He has worked in nuclear
power plants, natural gas co-generation facilities, hydrogen
plants and is expert in control systems design and implementation.
Heath Evenson joined CES in July as Operations Supervisor.
Heath began his career in the US Navy aboard nuclear submarines,
and is a graduate of the Naval Nuclear Power School. He also
has worked at a coal-fired co-generation plant in the operations
department. Plant administrative functions are handled by
Frances Landrum, who previously was the Plant Administrator
at an Edison Mission Energy cogeneration facility with more
than 60 employees. This team is responsible for the daily
operation of the Kimberlina power plant, which will be the
long-term test facility for future systems development.
(Last updated 12.16.04)
|